Decide where every power point, light, switch, fan and data point goes before rough-in, which happens once the frame is up and before the plaster goes on. Also lock in anything that needs a big cable or its own circuit, like an EV charger, induction cooktop, ducted air or a future battery. Changes after the plaster is on cost far more than changes on paper.
When does the electrical work happen in a new build?
In two stages. Rough-in happens once the frame and roof are on: cables are run through the frame, and boxes and brackets go in for every point, switch and light. Then the walls and ceilings are lined. Fit-off comes near the end, when the power points, switches, light fittings, fans and appliances are connected.
The rough-in is your last cheap chance to change your mind. After the plasterboard’s up, every extra point means cutting and patching.
What should I decide before rough-in?
Walk through each room in your head, then on the plans:
- Power points. Beside each bed, both sides. Behind the TV. At the bench where the coffee machine will sit. In the garage, the laundry and outside.
- Lights and switches. Which switch turns on what, and from which doorway. Two-way switches on stairs and long halls.
- Ceiling fans. Bedrooms and living areas. Mark the centre of where the bed or couch will go, not the centre of the room.
- Outdoor. Patio fans and lights, garden lights, weatherproof points, driveway lights.
- Data and TV. Where the modem, TV and home office go.
- Smoke alarms. Queensland has specific rules for new homes. Your builder and electrician set these out to the plan.
Mark it all on a copy of the floor plan. A plan with every point drawn on it is what the electrician sets out from, and it’s what you check against on site.
What future loads should I plan for now?
Some things are much cheaper to prepare for during the build, even if you don’t fit them yet:
- EV charging. A cable or conduit from the switchboard to the garage wall where a charger would go.
- Induction cooking. A dedicated cooktop circuit rated for induction, even if you start with something else.
- Solar and batteries. Space on and beside the switchboard, and a conduit path from the roof.
- Pool or spa. A circuit and conduit to where the equipment will sit.
- Shed or granny flat. A conduit under the slab or yard while the ground is open.
How big should the switchboard be?
Bigger than you need on day one. Every new circuit later, for an EV charger, a battery or a shed, needs space on the board. In Queensland, homes built since 2000 must have safety switch protection on all power point and lighting circuits, and the Electrical Safety Office recommends safety switches on every circuit. A board with room to grow avoids a switchboard upgrade down the track.
Do I need a separate electrician from the builder’s?
Most builders have their own sparky, and that works fine. Some owner builders and custom builds bring in their own. Either way, the electrician has to work to the builder’s program, so rough-in happens on time and the plasterers aren’t held up. Fins Up Electrical does new home rough-in and fit-off across Moreton Bay and works to the builder’s program. See new home electrical.
How do I check the plan before rough-in?
Ask for a walk-through on site once the frame is up. Stand in each room with the electrical plan and check every point, switch and light against how you’ll use the space. Move anything that’s wrong now. Fins Up Electrical quotes free and fixed before any work starts. Licence 91921. If you’re planning a charger, see EV charger installation.
Want this sorted? New home electrical from Fins Up.
Licensed electrician, licence 91921. Free quote before any work starts. Open 24 hours Monday to Saturday.
Common questions
What is electrical rough-in?
The stage after the frame is up where cables, boxes and brackets go in for every point, switch and light, before the walls are lined.
Can I add power points after the plaster is on?
Yes, but it means cutting into finished walls, which takes longer and costs more than adding them at rough-in.
Should I wire for an EV charger in a new home even without an EV?
It’s a smart move. Running a cable or conduit to the garage during the build costs much less than retrofitting later.